Project

General

Profile

Activity

From 09/20/2024 to 09/29/2024

09/26/2024

08:14 PM Support #1949 (Closed): system don't working
Mohamed Fareed
08:14 PM Support #1949 (Closed): system don't working
solved by restore the system icon to desktop Mohamed Fareed
08:06 PM Support #1945 (Closed): UBS REPLASED
Mustafa Hassan
08:06 PM Support #1945 (Closed): UBS REPLASED

The old UBS was removed due to damaged batteries and a new UBS was installed.
ِAnd Add CPU and RAM to the serv...
Mustafa Hassan

09/24/2024

05:55 PM HIS Support #1941 (Closed): juleb delivery medicine
Mustafa Hassan
05:55 PM HIS Support #1941 (Closed): juleb delivery medicine

I did the medicine delivery from the complex to the clinics.
Mustafa Hassan
04:56 PM HIS Support #1940 (Resolved): HIS integration with DHS & MDS
HIS integration with DHS & MDS Update Mohamed Fareed
04:47 PM Feature #1938 (Closed): Zatca Phase 2
Mohamed Fareed

09/22/2024

07:19 PM Support #1932 (Closed): Fingerprint Report
Mustafa Hassan
07:18 PM Support #1932 (Closed): Fingerprint Report
The fingerprint was taken and the report was sent to human resources and the complex manager. Mustafa Hassan

09/21/2024

02:31 PM Support #1925 (Closed): Sterilization Department
Mustafa Hassan
02:31 PM Support #1925 (Closed): Sterilization Department

I fixed a problem with the sterilization program.
Mustafa Hassan
 

Also available in: Atom