Project

General

Profile

Activity

From 07/01/2024 to 07/10/2024

07/08/2024

03:28 PM Support #1304 (Closed): IP PHONE
Mustafa Hassan
03:28 PM Support #1304 (Closed): IP PHONE

I CREATED DETAILS FILE FOR NEW IP PHONES AND SEND TO NETWORK MANAGER "ENG ABO SOFIAN"
Mustafa Hassan

07/04/2024

04:50 PM Feature #1128: ECR - Auto Payments - POS integration
Mohamed Fareed wrote:
> Devlopment the Payment of MADA POS Machines to be automatic sending from the system to the m...
Mohamed Fareed

07/03/2024

02:13 PM Support #1221 (Closed): support
Mustafa Hassan
02:13 PM Support #1221 (Closed): support

i fixed problem in accouantant exported reports keylink system
Mustafa Hassan
02:10 PM HIS Support #1219 (Closed): sdc problem
Mustafa Hassan
02:09 PM HIS Support #1220 (Closed): SDC NOT WORK STABLE
Mustafa Hassan

07/02/2024

01:57 PM HIS Support #1220 (Closed): SDC NOT WORK STABLE

Dear SDC Support, we have a problem in our branch after completing the SDC update
There is a duplicate registere...
Mustafa Hassan
01:28 PM HIS Support #1219 (Closed): sdc problem

i contacted with sdc support to resolve problem on sdc system
Mustafa Hassan

07/01/2024

01:57 PM Support #1198 (Closed): SUPPORT
Mustafa Hassan
01:56 PM Support #1198 (Closed): SUPPORT

I CREATED MAP DRIVE FROM MR FAHAD HR MANAGER PC TO SERVER .. TO COPY ALL DATA FROM DEVICE TO SERVER
Mustafa Hassan
01:45 PM Support #1197 (Closed): support
Mustafa Hassan
01:44 PM Support #1197 (Closed): support
I CHANGED MONITOR FOR MR ABDELMALEK ..HR Officer Mustafa Hassan
11:23 AM Support #1195 (Closed): FINGERPRINT
Mustafa Hassan
11:22 AM Support #1195 (Closed): FINGERPRINT
ADD DR GEHAD USER TO BRANCH FINGERPRINT Mustafa Hassan
11:12 AM Feature #1193 (Closed): REPORTS
Mustafa Hassan
11:11 AM Feature #1193 (Closed): REPORTS

The July sales report file was prepared and sent to the branch manager
Mustafa Hassan
 

Also available in: Atom