Project

General

Profile

Activity

From 09/20/2024 to 09/29/2024

09/24/2024

04:56 PM HIS Support #1939 (In Progress): HIS integration with DHS & MDS
HIS integration with DHS & MDS Update Mohamed Fareed
04:47 PM Feature #1936 (Closed): Zatca Phase 2
Mohamed Fareed
04:46 PM Support #1935 (Closed): Upgrade DB
Mohamed Fareed
04:46 PM Support #1935 (Closed): Upgrade DB
Upgrade Oracle DB to be compatible with Win Server 2019 and to be ready for Zataca And DHS-Naphise integration Mohamed Fareed

09/22/2024

07:12 PM Support #1929 (Closed): Fingerprint Report
Mustafa Hassan
07:12 PM Support #1929 (Closed): Fingerprint Report

The fingerprint was taken and the report was sent to human resources and the complex manager.
Mustafa Hassan

09/21/2024

02:26 PM Support #1924 (Closed): Server Ubgrade
Mustafa Hassan
02:26 PM Support #1924 (Closed): Server Ubgrade

I went to the branch on Friday.. Upgraded Ram to 128 GB And Upgrade win server to 2019
And ubdate All pcs in br...
Mustafa Hassan
 

Also available in: Atom