Project

General

Profile

Activity

From 09/13/2024 to 09/22/2024

09/22/2024

07:12 PM Support #1929 (Closed): Fingerprint Report
Mustafa Hassan
07:12 PM Support #1929 (Closed): Fingerprint Report

The fingerprint was taken and the report was sent to human resources and the complex manager.
Mustafa Hassan

09/21/2024

02:26 PM Support #1924 (Closed): Server Ubgrade
Mustafa Hassan
02:26 PM Support #1924 (Closed): Server Ubgrade

I went to the branch on Friday.. Upgraded Ram to 128 GB And Upgrade win server to 2019
And ubdate All pcs in br...
Mustafa Hassan

09/18/2024

04:01 PM HIS Support #1915 (Closed): add user
Mustafa Hassan
04:01 PM HIS Support #1915 (Closed): add user
Create a user for a gynecologist on the key link system Mustafa Hassan
 

Also available in: Atom